Power Machines completed installation of a stand for assembling the combustion chambers of high-power gas turbines

Installation of a stand for assembling the combustion chambers of high-power gas turbines was completed in the assembly shop for gas turbines of the Leningradsky
Metallichesky Zavod (LMZ) of PJSC «Power Machines».

The stand is designed for the simultaneous assembly of four combustion chambers with an internal heat-resistant mixer, burner arrangement, thermal protection ceramic tiles, as well as external thermal insulation of the chamber and installation of its sheet shell.

The stand was installed as part of the retrofit program for some groups of equipment necessary for the production of gas turbines GTE-65 and GTE-170.